The Ministry of Public Construction (MOP), has rejected the installation of a meccano bridge in order to replace the failed Cau Cau. Currently, National and International companies are disputing the tender to design the reparation of the viaduct.

In the fifth reunion of citizen participation realized to inform about the construction avances of the bridge, the General director of the MOP, Juan Manuel Sánchez, discarded the installing of a meccano bridge as was solicited by the population and the parlamentarians.

According to Sanchez explanation, this alternative is unfeasible because it would cost 5200 million pesos and would take 240 days to be implemented. For that reason will be analyzed the installation of a permanent or movable platform for the transit of vehicles.